Employed to complete all aspects of Formwork, steel fixing and concrete pouring and finishing.
Mainly taking part on the constitution of stormwater pits and culverts from steel fixing, formwork and concrete pours for new housing estates in the Melbourne area and surrounding suburbs.
Formwork Carpenter
Connor Concrete and Formwork Metro Tunnel South - CYP
Melbourne, VIC
06.2022 - 11.2022
Employed to complete additional works won by Connors, I commenced works in the yard to assist with the construction of emergency exit tunnel shutters.
Soon after starting in the yard i was moved underground at the Federation Square site and commenced work there, both on day and night shift.
Daily pre-starts and start cards prior to work.
Forming bemas and stop ends and assisting with columns.
Working within a team on suspended precast panels. Using conventional and Peri system decks and walls.
Steelfixing to stitch beams.
Assisting concreters with setting up pumps and pours when needed.
Setting up PTLF and CMC machines ready for pours.
Carpenter Subcontractor
Jaycon Building Group Chisholm Rd - Lara
Melbourne, VIC
09.2020 - 02.2022
Working under Jaycon Building Group and the head contractor John Holland we were tasked to complete 1248 steel cell doors and over 1200 timber doors ranging in size and levels of security.
Managing supply and stock level's throughout the project.
Carpenter Subcontractor
Jaycon Building Group Cherry Creek Youth Justice - Little River
Melbourne, Vic
09.2020 - 02.2022
While working across Chisholm Rd Prison i was simultaneously woking on the Cherry Creek Youth Justice Centre again under Jaycon Building Group and head contractor John Holland.
Myself and another employee were engaged to complete the steel cell doors for the entire prison . we also undertook the the installation of complicated prison cell door hardware and installation of prison security Polycarb windows.
Managing supply and stock levels throughout project.
Carpenter Subcontractor
Jaycon Building Group Cotton On - Geelong
Melbourne, Vic
12.2019 - 12.2019
Completed works on the Cotton On wellness centre.
The works in the Wellness Centre included extensive Tallowwood wall cladding, installation of doors and door hardware throughout.
Managing supply and stock levels throughout the project.
Carpenter Apprentice
Eastrise Construction
Melbourne, Vic
03.2016 - 09.2019
Jobs in the South East of Melbourne such as high end renovations and new builds, demolition and clean up.
Working alongside 2 qualified carpenters undertaking all aspects of carpentry.
Completing a wide range of tasks such as cleaning, framing, lock up and fix, demolition and assisting other trades when needed.
Education
High School Diploma -
Craigieburn Secondary College
Craigieburn
Apprenticeship Group Australia
Certificate II Carpentry
Apprenticeship Group Australia
Certificate III Carpentry
White Card
Victorian Driver License
Metro Academy
Rail Tickets
Timeline
Formwork Carpenter
Symon Bros Construction
01.2023 - Current
Formwork Carpenter
Connor Concrete and Formwork Metro Tunnel South - CYP
06.2022 - 11.2022
Carpenter Subcontractor
Jaycon Building Group Chisholm Rd - Lara
09.2020 - 02.2022
Carpenter Subcontractor
Jaycon Building Group Cherry Creek Youth Justice - Little River