Summary
Overview
Work History
Education
Timeline
Generic

JAY THAMPI

Summary

ABOUT ME: With over 12 years in the construction industry, Jay has worked on some of Australia's most significant construction projects and projects internationally. Jay started his career in construction as a labourer and machine operator. A few years later, he began working as a lab technician for asphalt and quarries. Over the past years, Jay has worked in leadership positions with industry leaders such as John Holland, CPB/John Holland JV, and Atkins. Notably, he worked as a Senior Project Engineer for the Hong Kong International Airport Third Runway Project (HKIA 3RS)

Overview

11
11
years of professional experience

Work History

Avionics – Project Manager

RAAF Base
Darwin
08.2023 - Current
  • Project lead for Airfield Ground Lighting works in RAAF Darwin

Project Manager

AVIONICS PTY LTD & AVIONICS AIRFIELD LIGHTING PTY LTD
08.2023 - Current
  • Direct report to Company Directors, leading the delivery of AGL works at RAAF base Darwin (P0009)
  • Built a team to deliver airside works, including onboarding, training and ongoing management of delivery team, subcontractors, and direct labour;
  • Successfully established a precast yard in Darwin, producing over 200 precast elements;
  • Lead the delivery of runway displacements, ensuring compliance as per MOS139 specifications;
  • Liaison with authorities for NOTAMs and works access;
  • Accountable for the capital and operational budget expenditure, reporting cost to date and monthly cash flow forecasts to Company Directors.

Project Engineer

John Holland
01.2023 - 08.2023
  • West Gate Tunnel Project (WGTP) – West Zone
  • West Gate Freeway Widening
  • Forecasting/budget management; delivery of RC structures, heavy civils, lifting operations, traffic interface, client and council relations.

Project Engineer

JOHN HOLLAND GROUP, West Gate Tunnel
01.2023 - 07.2023
  • Leading a team of engineers to deliver civil works along the Verges of the West Gate Freeway and structural works under Millers Road Bridge
  • Managed allocated cost codes and set budgets, commercial management
  • Concurrent management of eight work fronts, including both self-perform and contract works
  • Select and onboard subcontractors, negotiate rates, and lsum contracts
  • Fostering positive relations with the local council during the reinstatement of council assets along freeway verges
  • Successfully delivered all works safely and within budget with traffic closure constraints, unknown underground services, community interface, union, and design issues.

Senior Project Engineer

Atkins, Airport Authority
01.2022 - 01.2023
  • Hong Kong International Airport New Third Runway Project
  • Delivery lead for asphalt, pavement design and DLP repairs; CapEx and OpEx management; liaison with government/client.

Senior Project Engineer

ATKINS – AIRPORT AUTHORITY HONG KONG
01.2022 - 01.2023
  • Promoted by the Airport Authority Hong Kong whilst on secondment, to manage the Asphalt works of the New Third Runway and the rehabilitation of the second runway and taxiways
  • Working under the 3303, 3310 and 3913 NEC contracts, reporting to the Principal Manager of the Airport Authority
  • Construction and commercial management
  • Responsible for managing JV contractors and self-perform crews on a 24/7 roster and for managing 8- and 12-week look-ahead programs
  • Determining future requirements, including machine tools, ancillary equipment, major plant and labour
  • Managing budget expenditure to maximise the profit margin for the project
  • Average placement of 4,000t of hot mix asphalt and/or 3,000t of polymer modified asphalt per day and all associated field and production testings
  • Providing priorities and managing the interface between Aggregate, Airfield Ground Lighting (AGL) and Underground Utilities teams
  • Implementing cost effective defect rectification within NOTAM hours and emergency repairs
  • Completing 240,000m2 of grooving and all line marking for the Runway, Taxiway, Airside and Landside Road
  • Liaison with Government Authorities and other Airport Authority internal stakeholders (Airfield Department, Facilities Planning and Technical Service Infrastructure Department) during the staged handover/commissioning period and DLP period
  • Design input and development
  • Resolving pavement settlement issues with grade corrections as construction was done on a reclaimed land
  • Developing asphalt mix designs and performance testing for 3303 and 3913 contract – Runway, Taxiways, Airside Road and Landside Road
  • Evaluating pavement structure using a Heavy Weight Deflectometer to assess the pavement strength for aerodrome licensing, expressed as a Pavement Classification Number (PCN)

Project Engineer

Atkins, Seconded, Airport Authority
08.2021 - 12.2021
  • Hong Kong International Airport New Third Runway Project
  • Project management for delivering pavement construction and subgrade stabilization.

Project Engineer

New
09.2021 - 12.2021
  • Seconded to Airport Authority Hong Kong to manage the preparation of subgrade and construction of Sub Base/Base Course Aggregate Pavements for the New Third Runway and Taxiways constructed on reclaimed land – Working under the 3303 NEC contract
  • Maintaining cost and resource forecast, budget expenditure and 4-week look ahead programs
  • Managing a 24/7 roster team of 3 Site Engineers, 2 Assistant Engineers and 3 Site Managers
  • Resolving issues related to constant settlement and variable fill (reclaimed land)- Approximately 250,000t of subgrade removed and replaced; 300,000t of crushed aggregate placed to regulate settlement
  • Maintained daily laying average of 8800t of aggregate pavement per shift (not including levelling), 17500 m2/day cement stabilisation and all associated field and production testings
  • Ensuring QA work lots and design changes are approved by the Authority stakeholders and liaising with Government Authorities for seeking Building Department (Hong Kong Government) approvals
  • Page 5 of 5
  • Page 1 of 5

Site Engineer

John Holland, WGTP
01.2021 - 08.2021
  • West Zone
  • West Gate Freeway Widening
  • Heavy civil operations, incl
  • Traffic switches along major roads; QA management; forecasting/cost management.

WGTP, East Zone
01.2020 - 01.2021
  • Port to City elevated structures and at-grade civil works
  • Design and interface management, expenditure management, client relations, stakeholder management, CPS management

WGTP
01.2019 - 01.2020
  • Tunnel Zone
  • North Portal, Tunnel Back End Works
  • Delivered RC heavy structures, heavy lifts, civil operations, tunnel, and portal drainage

Goulburn Murray Water Connections Project
Shepperton
01.2018 - 01.2019
  • ECI/Delivery: pipelines and meter outlets, estimation, survey

Plant Operator/Laborer

O’ Malley Civils, Unsealed Roads
Alice Springs, NT
01.2017 - 01.2018
  • Survey, OHS, machine operations, mass haul management

Lab Technician

Fulton Hogan
11.2013 - 11.2016
  • Asphalt and quarry QA/QC, Asphalt mix design (PMB and Pen-grade), machine operations.

Education

Bachelor of Engineering - Civil and Infrastructure

RMIT University Tickets

Timeline

Avionics – Project Manager

RAAF Base
08.2023 - Current

Project Manager

AVIONICS PTY LTD & AVIONICS AIRFIELD LIGHTING PTY LTD
08.2023 - Current

Project Engineer

John Holland
01.2023 - 08.2023

Project Engineer

JOHN HOLLAND GROUP, West Gate Tunnel
01.2023 - 07.2023

Senior Project Engineer

Atkins, Airport Authority
01.2022 - 01.2023

Senior Project Engineer

ATKINS – AIRPORT AUTHORITY HONG KONG
01.2022 - 01.2023

Project Engineer

New
09.2021 - 12.2021

Project Engineer

Atkins, Seconded, Airport Authority
08.2021 - 12.2021

Site Engineer

John Holland, WGTP
01.2021 - 08.2021

WGTP, East Zone
01.2020 - 01.2021

WGTP
01.2019 - 01.2020

Goulburn Murray Water Connections Project
01.2018 - 01.2019

Plant Operator/Laborer

O’ Malley Civils, Unsealed Roads
01.2017 - 01.2018

Lab Technician

Fulton Hogan
11.2013 - 11.2016

Bachelor of Engineering - Civil and Infrastructure

RMIT University Tickets
JAY THAMPI