Asphalt Project Engineer, Various Clients – Western Australia.
City of Wanneroo – Hepburn Avenue Road Widening
- Delivered road widening and full pavement upgrade works on Hepburn Avenue, including drainage installation, box-out, subgrade preparation, base preparation, and placement of multiple asphalt layers.
- Duties: Prepared and maintained daily run sheets, site diaries, and QA checklists; carried out temperature checks, edge pressing, and compaction testing; measured daily output, calculated areas, and tonnages; tracked proforma targets for labor, plant, and material productivity; analyzed variances, and adjusted daily crew output to meet efficiency benchmarks; conducted claims preparation, and ensured execution within project scope; raised variations, and submitted technical queries (TQs) for scope clarification; liaised with council inspectors and residents for access coordination; oversaw sweeping and final prep before asphalt laying; ensured compliance with the Noise Management Plan and environmental controls.
Town of Mosman Park – Local Lane Resurfacing
- Managed multiple profiling and asphalt resurfacing projects across residential lanes.
- Responsibilities included: Managed run sheets, QA inspections, and client coordination; verified mat temperatures, compaction, and edge conformity; maintained proforma tracking of material use, crew performance, and daily machine hours to optimize operational cost per m²; raised TQs and variations for unforeseen pavement and subgrade issues; ensured night works met environmental and noise limits.
Town of Cottesloe – Dean Street & Griver Street Upgrades
- Delivered full road rehabilitation, including profiling and resurfacing
- Accountabilities: Managed testing procurement, QA reporting, and run sheets. Raised TQs for conflicting survey and design information. Oversaw joint prep, temperature logs, and final surface QA. Coordinated claims for variations due to latent conditions. Monitored proforma performance vs. Actuals across asphalt, profiling, and sweep teams to ensure cost alignment. Maintained resident communication, and ensured minimal disruption.
CBH Group – Regional Access Roads & Great Eastern Highway Patches
- Delivered prime coat, two-coat seal, and DGA asphalt on regional access roads.
- Managed profiling and asphalt patching on Great Eastern Highway.
- Tasks included: Prepared and submitted claims, variation requests, and TQs; managed material procurement, quality documentation, and subcontractor coordination; conducted sweep checks, surface temperature monitoring, and rolling compliance; tracked pro forma reports for regional crew output and compared them against bid estimates to ensure cost recovery.
BMD – Graham Farmer Freeway Overlay Works
- Delivered profiling and asphalt overlay on a high-volume freeway section.
- Responsibilities included: Oversaw lane closures, night shift logistics, and contractor management; prepared run sheets, QA reports, and verified surface temps and roller passes; raised TQs and submitted claims and variation documentation; reviewed proforma data to ensure productivity goals were met under live traffic constraints; ensured sweeping and tack prep was complete prior to paving.
Civicon – Transperth Parking Upgrades
- Completed asphalt surfacing works for Transperth commuter car parks.
- Duties included: Reviewed pre-paving compaction reports, kerb alignments, and site readiness; coordinated sweeping, QA checks, and run sheets; verified asphalt thickness, joint quality, and compaction; managed testing procurement, and communicated with Civicon and Transperth stakeholders; monitored proforma performance across multiple car parks, highlighting delays or production gains for reporting to the PM; raised TQs for undocumented services or layout conflicts.