Overview
Work History
Education
Skills
Interests
Timeline
Generic

Vallinayagam Selvaraj

Point Cook,Australia

Overview

25
25
years of professional experience

Work History

Lead Cost Controller

ARTC (Australian Rail Track Corporation)
10.2022 - Current
  • Submission of Monthly Cost Reports to IR Corporate team based in Brisbane
  • Review of Contractors Progress Claims and certification of invoices for payments
  • Review of Contractor’s forecast and variations, including Risk and Contingency items
  • Prepare lessons learnt information for identifying the cost impacted items
  • Attend Cost review meetings with the Contractors and discuss the basis of cost forecast
  • Provide cash flow forecasts to IR Corporate for FY budget allocation

Senior Cost Controller

Rail Projects Victoria
09.2018 - 10.2022
  • Submission of Monthly Cost Reports to MTIA for the handled packages Rail Signaling, Land Acquisition
  • Review of Alliance Contractors Progress Claims and certification of invoices for payments
  • Conduct financial audits on the projects, with a focus on contractor cost and revenue forecasts
  • Prepare benchmarking data for Rail Signalling work package to identify trends within the project
  • Attend Cost review meetings with the Contractors and discuss the basis of cost forecast
  • Provide cash flow forecasts to Treasury for financial year budget allocation

Senior Cost Controller

Downer Group
07.2010 - 09.2018
  • Provide cost analysis on actual, cash flow, forecast cost and progress performance
  • Ensure development and issue of planning and progress reports (VOWD & COST FORECAST), profiles, man-power histograms etc
  • Maintain and administer the maintenance cost control system and ensure interfaces between the cost control systems are accurate
  • Develop Work Breakdown Structure (WBS) and other coding in line with internal, contract and work face planning requirements for use in scheduling and progress system
  • Ensure alignment between scheduling and progress system

Manager - Contracts

EMAS Engineers & Contractors
12.2009 - 05.2010
  • Preparation of Contract documents for various Projects
  • Preparation of Bank Guarantees, Performance Bonds & Insurance
  • Monthly Client Billing & Payment status of all projects
  • Preparation of MIS reports on monthly basis
  • Major Projects under taken: TICEL Bio Park II (US$ 20 Million) - Project cost control, Contracts management

Quantity Surveyor

Aker Solutions
09.2008 - 06.2009
  • Preparation of Monthly Progress Bill for the Contractor’s Claims (M/s
  • Downer – M/E works and M/s
  • Monadelphous – Structural Steel works)
  • Preparation of weekly progress reports based on the actual works at site
  • Preparation of Contractual correspondence with the Client and Contractors
  • Preparation of Budget estimates for cost implications arising from Variations
  • Preparation of final estimated quantities for evaluating the progress of work at site

Senior Quantity Surveyor

Dutco Balfour Beatty
06.2007 - 08.2008
  • Evaluate design changes and prepare cost estimate for Notification of Variations
  • Preparing Bid tab summaries for review and approval of Sub-contractors and Suppliers
  • Preparation of Sub-contract Agreements for various trades involved in the project after getting approval from the senior management
  • Preparation of Contractual correspondence with the Consultant and Sub-Contractors
  • Prepare and maintain standard procedures in Construction department in relation to Contracts and Quantity Surveying practice in co-ordination with contract head
  • Identification of cost overrun areas in different stages of procurement and undertake cost saving calculation exercise in terms of Value Engineering etc
  • Prepare cost information used in Budget forecasting

Quantity Surveyor

KEO International Consultants
05.2005 - 05.2007
  • Major Projects under taken: Porto Arabia, The Pearl Qatar – Preparation of Tender Documents for 40 Packages (US$ 2.5billion)
  • Infrastructure Development for Mohamed bin Zayed City, Abu Dhabi – Preparation of budget estimate for infrastructure works (US$ 157 million)
  • Ghobash Tower Project, Dubai – Preparation of BoQ and Estimate (US$ 250 Million)
  • Coral Reef Tower, Ajman – Preparation of BoQ and Tender Analysis Report (US$ 400 million)

Quantity Surveyor

Six Construct Co. LLC
06.2002 - 05.2005
  • Preparing Interim valuations for Payment certificates
  • Preparation of Quantity calculation for material procurement, estimations and rate analysis for new items
  • Evaluating Sub-contract variations, preparing sub-contract agreements and Sub-contractor monthly interim payment certificates
  • Contractual negotiations with the consultant regarding monthly payment certificates, variation works, claims and quantity reconciliations
  • Assisting Commercial Manager for preparation of claims, maintenance of records for delay in works, obstructions and client instructions

Project Associate

Indian Institute of Technology
07.2001 - 04.2002

Civil Engineer

Venus Civil Engineers
06.2000 - 06.2001

Education

Bachelor of Engineering - Civil

Madurai Kamaraj University
Madurai, India

Skills

  • Cost benchmarking
  • Supplier relationship management
  • Cost reconciliation
  • Earned value management

Interests

Cricket umpiring, gardening

Timeline

Lead Cost Controller

ARTC (Australian Rail Track Corporation)
10.2022 - Current

Senior Cost Controller

Rail Projects Victoria
09.2018 - 10.2022

Senior Cost Controller

Downer Group
07.2010 - 09.2018

Manager - Contracts

EMAS Engineers & Contractors
12.2009 - 05.2010

Quantity Surveyor

Aker Solutions
09.2008 - 06.2009

Senior Quantity Surveyor

Dutco Balfour Beatty
06.2007 - 08.2008

Quantity Surveyor

KEO International Consultants
05.2005 - 05.2007

Quantity Surveyor

Six Construct Co. LLC
06.2002 - 05.2005

Project Associate

Indian Institute of Technology
07.2001 - 04.2002

Civil Engineer

Venus Civil Engineers
06.2000 - 06.2001

Bachelor of Engineering - Civil

Madurai Kamaraj University
Vallinayagam Selvaraj