Proficient Project Engineer with 10 years of experience driving over 5 projects to completion. Skilled in overseeing technical staff and checking that projects are completed on schedule, within budget and according to specifications. Organized and dependable candidate successful at managing multiple priorities with a positive attitude. Willingness to take on added responsibilities to meet team goals.
1. Rehabilitate of Sewage Treatment Plant Facility specially sequencing batch reactor (SBR).
2. Rectification of Automatic Fire Sprinkler System as per fire code.
3. Upgrading of 4-unit Transfer Pump soft starter control panel
4. Completion and Acceptance of 3-unit Mitsubishi Elevator System for Tower 5. (Replacement of 6-Hoisting Rope)
6. Rehabilitate Electrical System & Automatic Transfer Switch for Generator
I handle Avida Towers Centera a four (4) high rise condominium & commercial Towers (32 floors each) for the operation an maintenance of the equipment. During my time I handled various upgrade and rehabilitation:
1. Rehabilitate of Sewage Treatment Plant Facility specially sequencing batch reactor (SBR).
2. Rectification of Automatic Fire Sprinkler System as per fire code.
3. Upgrading of 4-unit Transfer Pump soft starter control panel
4. Completion and Acceptance of 3-unit Mitsubishi Elevator System for Tower 5. (Replacement of 6-Hoisting Rope)
6. Rehabilitate Electrical System & Automatic Transfer Switch for Generator
Assist in developing, reviewing, updating, modifying, and approving mechanical design plans, mechanical work practices and work schedules.
Conduct regular equipment preventive maintenance and recommendations as per actual condition. Provide technical report and parameters of the testing conducted during the activity. Review and check engineResponsible for overseeing the building preventive maintenance, planning and inspection and function of the facility of the building