Undergraduate Engineer
Projects:
Harmony Stage 3, Little Springs Estate Stage 1, and Majesty Stage 1:
- Updated invoices of ordered materials, labour costs, and machinery dockets into kynection using necessary cost codes.
- Sent Request For Quotation (RFQ's), Request for Information (RFI's) through Outlook.
- Evaluated material cost provided by multiple subcontractors, responsible for reviewing the best price among obtained quotations and prepared purchase orders using Excel.
- Lodged DBYD request. Curated and organised DBYD responses.
- Captured ITP photos using Timestamp and organised the documents.
- Interpreted construction drawings (Blueprints) and drawn utility service locations on plans using PDF-Xchange Editor.
- Worked closely with engineers and assisted in site visits prior and after the earthworks, installation of utility services and construction of pavement.